Tuesday, September 22, 2020

August 2020

 We continued in August with "2-a-weeks," that is, two work sessions a week with the goal of moving 470 to Antonito in mid September.  As many of you know the move was completed on schedule on 18-19 September.  In this post we will review the efforts and accomplishments that allowed this to happen during the month of August.


Dean, as one of the younger people in our group, took over the work on the clerestory.  The platforms and scaffolding on the sides were removed to install siding so he had to use ladders.  In this photo he is installing one of the "teardrop" panels in the end of the clerestory.





Here Dean is shaping one of the panels to fit.









A panel in place and primed.







This one is in color.







The clerestory window screens were painted prior to installation. John E. is doing the work here.









This photo shows a screen ready to be screwed in place.  A spacer board can be seen at the right edge of the photo.  These were used to cover the framing where double framing members were present as can be seen to the left of the screen.





This photo shows a finished end section.

The window frames and body framing were primed and painted before the screens were installed, here by Tom.







There was quite a bit of prep work involved before we could apply the primer to the upper part of the car body.  Here Wayne is doing some scraping around the windows.






Don is doing some sanding.







Bill L. is scraping.










John C. is taping windows prior to priming.







Next was priming the upper part of the body around the windows.  Don is shown here but there were many participants.  The priming was done by hand but arrangements were made to have Brad come and spray the color.





Bill K. priming the west end.







Dean priming the overhang.










Good job, everyone.









We had to re-prime the siding boards to be compatible with the paint to be used, but first sanding was required.  Craig and Don are sanding.






The siding boards were installed, Craig using a nail gun in this photo.









The siding was glued on as well as nailed.  Ron is applying the glue in this photo.  The siding originally was glued with hide glue which had lost most of its adhesive qualities when we removed the old siding.




The siding was installed and primed by the end of August.








The upper sashes on the car body windows were screwed to the frames.  They were not meant to open but were somewhat loose in the channels so were secured.  Also in this photo note that the windows have been covered in paper prior to spraying the color coat on the car.




 The exterior doors also were taped and covered with paper as it was decided to paint these by hand.










The pull cord straps are assembled and ready to install.







Ron has installed them in the ceiling as shown here.  The cord will pass through the brass ring at the bottom and run the length of the car.








The cord passes through the cabinets at each end of the car and these rings will be installed in the front of the cabinets for the cord.






This photo shows a ring in one of the overhead cabinets.






One of the doors is original and this photo shows a brass shield over the key hole which was preserved.  The one at the other end of the car was missing, however.





Ron was able to reproduce one in brass, the shiny one on the right being the new one which will be installed on the other door.






The car is scheduled to be spray-painted on September first so this was a busy month.  More to come.

Thanks to Tom, John, and Don for contributing photos.

Friday, August 14, 2020

July 2020 - Warp speed.

With deadlines approaching July was a busy month.  Two work days a week were scheduled and well attended.  Construction  was winding down and efforts turned to scraping, sanding and painting.

Wayne and I installed the last of the louvers.





They look nice in the windows as well as provide some protection from the sun.








Craig made trim strips to go below the louvers to cover up the old framing.  These were screwed in place.











Then treated with clear sealer.









The primary construction project during this time was installation of the upper berths.  First the hinges were installed.






The platforms are heavy and bulky with a narrow aisle in the car to navigate.  Here Wayne and Don are doing the heavy lifting.








Getting the platforms in position was a three person job by Ron, Wayne and Craig.






Craig built an adjustable frame to stabilize the platforms.  The aisle edges are resting on the brass fittings in the seat posts and the far edge is adjusted until level.







Finally the hinges were screwed into the wall of the car.







Occasionally some fitting was necessary so the berth could move up and down freely.








There were some parts not used in the latch to hold the berths in the "up" position so Ron re-engineered them to make safety catches.  In this photo he has removed one end of a couple of the these pieces.







This photo shows part of the brass has been ground away.









I am skipping ahead into August with this photo but it shows one of the latch locks fastened in place with the flange over the top of the hinge to prevent it from releasing.  Also of note in this photo is the number "4" above the latch.  Each berth is numbered with a decal in the same order that was done originally.  There are a total of ten, five on each side of the car.




The water tanks in the men's washroom have been installed.  They are filled from above through the vent in the ceiling.











The round cap with the handle covers the filler access for the water tanks.








Craig had a double walled vent made for the stove to vent through the roof.








The vent has been installed in the corner next to the women's lavatory where the stove will be.







Installation of the clerestory windows was completed this month.  I believe that is Dean's watch in this photo.






Tom made a cardboard pattern for the siding piece in the "teardrop" area under the curved overhang.







Then Craig made the wood to fit.








A lot of time was devoted to sanding this month.  Bill L. is working on the platform steps.







Dean is sanding the clerestory.







Bill L. is scraping and sanding siding.







Wayne is sanding siding for the lower part of the car.  It was primed previously and stored.









As was mentioned previously the clerestory windows are being fastened in place and will not open.  Dean is applying caulk around the edges.






Tom is doing some scraping and priming on the clerestory.






Bill K. braved the Gap to help with the priming.



Thanks to Tom and Don for contributing photos.