Glue was applied to each layer, and clamps applied at close intervals along the length of the beam. In the photo on the left, John is applying glue, while Tom, Craig, and George are supplying moral support. On the right, above, John is tightening one of many clamps used.
On Saturday, after clamp removal, the beam was run through the planer several times to get it down to the proper dimensions, and taken several blocks to the work site as shown on the right, above. It even looks quite straight. The sill that will be replaced is the lower one adjacent to the new beam. The vertical and horizontal framing members are mortised into the existing sill, so more work will need to be done on the new one before it is ready.
Craig has also been busy with other things. He has built new doors using the original hardware (cleaned up beautifully), with molding and sliding windows duplicated from the the old ones. He also has made arched carlines to replace bad ones as necessary in the roof structure.
Meanwhile, on our regular work session on Saturday, most of the west platform has been uncovered showing the framing structure. The platforms are cantilevered from the under carriage of the car, and were finished with tongue-and-groove decking that is quite deteriorated.
Bob and I continued cutting and threading tie rods to replace rusted ones. We finished this project on Saturday, and made some extras, as well as threading pieces for use in the future on other projects. Note the always handy roll of duct tape.